14th January to 11th of February - Implementation:​
Development Sprint 1 (1 week): Create CLI, issue branch and basic issues​
Development Sprint 2 (1 week): Create detailed issues, view, comment on and update issues​
Development Sprint 3 (0.5 week): Basic synchronising with other repositories (ignoring merging issues)​
Development Sprint 4 (1.5 week): Complete synchronisation with other repos – all system functionality completed​
Documentation for each sprints results ​


12th of February to 21st of February - Testing:​
Create testing strategy: Black-box (unit testing), integration testing​
Fix any bugs highlighted from testing and document them​
Testing documentation (verification and validation section of report)


22nd of February to 22nd of March – Report writing:​
1st week: Create report introductory pages, introduction section and finish problem description and specification section of report ​
2nd week: System design section of report, user and technical guide, installation guide, maintenance and developer guide​
3rd week: Detailed design and implementation section of report​
4th week: Results and evaluation section, summary and conclusion of project ​


23rd of March to 25th of March - Submission:​
Report review: proof reading, formatting, polishing​
Submit project​


27th of March - Demo:​
Project Demonstration