14th January to 11th of February - Implementation:
Development Sprint 1 (1 week): Create CLI, issue branch and basic issues
Development Sprint 2 (1 week): Create detailed issues, view, comment on and update issues
Development Sprint 3 (0.5 week): Basic synchronising with other repositories (ignoring merging issues)
Development Sprint 4 (1.5 week): Complete synchronisation with other repos – all system functionality completed
Documentation for each sprints results
12th of February to 21st of February - Testing:
Create testing strategy: Black-box (unit testing), integration testing
Fix any bugs highlighted from testing and document them
Testing documentation (verification and validation section of report)
22nd of February to 22nd of March – Report writing:
1st week: Create report introductory pages, introduction section and finish problem description and specification section of report
2nd week: System design section of report, user and technical guide, installation guide, maintenance and developer guide
3rd week: Detailed design and implementation section of report
4th week: Results and evaluation section, summary and conclusion of project
23rd of March to 25th of March - Submission:
Report review: proof reading, formatting, polishing
Submit project
27th of March - Demo:
Project Demonstration